As a follow up to the Dec 19 message regarding UCM Plan Enhancement Project: Latest Developments, note the following updates and changes that will impact various administrative staff as part of the UCM Plan Enhancement Project:
-
Test Environment Access: Reviewed with department financial leads in early January 2025.
-
Submit Access Requests: Department leads must submit any new or revised access requests via a Service Now ticket as needed.
-
Test Environment Exploration: Users have access to explore the new environment and begin re-creating current SmartView reports in the test environment.
-
Upcoming Trainings (Week of March 3)
-
Supplemental UCM Plan Enhancement
-
Budget Request Fundamentals
-
Workforce Fundamentals
-
Session content details and training invitations will be provided in separate communication.
-
Confirm Access and SmartView Usability: Ensure proper access has been requested, confirmed, and validated. Users should confirm their ability to use SmartView prior to go-live.
SmartView Access Changes
-
Project Cube Access Removal:
-
Task-level data reporting will no longer be available in SmartView.
-
SmartView will support GL and PPM project-level reporting directly from the Financial Cube (GL data only).
-
System Freeze Information
To ensure a smooth transition for the March 21 go-live, note the following system availability schedule:
-
March 10 – 19 – Budget requests cannot be processed, but data remains available for reporting.
-
Thurs March 20 – System will be completely offline for go-live preparations.
-
Fri March 21 – System will be available with all enhancements.
Stay Updated
As the project continues to progress until the March go-live date, visit our UCM Plan Enhancement website for the most up-to-date updates. Please reach out to dofa@ucmerced.edu with any questions, and a member of the project team will be in touch.